What to Know About Cathodic Protection in Indiana
Indiana requires IDEM certification under IC 13-23 for whoever supervises, manages or directs cathodic protection work on a UST. IDEM's Office of Land Quality enforces corrosion protection under 329 IAC 9, which adopts 40 CFR 280 by reference. The incorporated federal text is the edition the rule names, unless the rule says otherwise. CP work keeps buried steel protected with sacrificial anodes or an impressed current rectifier, and IDEM certificates cover only the exam subjects their holder passed. Buyers near Indianapolis should check that the seller's last two CP testing reports exist, because IDEM cites missing ones, and budget with Phase I ESA pricing for Indiana sites.
Parts of the rule text still name the State Fire Marshal, but IDEM has run UST certification since July 1, 2023. Two IDEM violation letters from spring 2024 cite section 280.31(b) of the federal CP rule for a missing three-year CP test, and one involved sti-P3 tanks with factory-installed anodes. Notification forms filed with IDEM also show whether each steel tank relies on sacrificial anodes or impressed current, so a tester can confirm the system on file before arriving. Before shortlisting cathodic protection companies in Indiana from the Indiana UST contractor list, ask who will direct the work and which IDEM certificate categories that person holds.
Indiana sets the cost of breaking its UST rules, the incorporated CP rules included, at a civil penalty per tank for each day of violation under IC 13-23-14-3. Annual tank fees add $90 per regulated petroleum tank, listed on IDEM's regulated storage tanks page, and IC 13-23-12-1(c) bills each compartment separately. The ELTF 50% program can repay up to half of eligible decommissioning costs, which matters if a failed CP system pushes an owner toward closure. Name the tank count, system type, metal piping runs and any failed survey when you request Indiana corrosion quotes.
Because 329 IAC 9-1-1 folds in the federal standard, cathodic protection testing in Indiana starts within six months of installation and repeats at least every three years. On the day of the visit, the person directing the work must display or produce an IDEM certificate, under 329 IAC 9-10. IDEM inspectors ask to see the rectifier log and the latest three-year report. If digging to an anode bed at a Gary or Evansville station exposes stained soil, crews handling that suspected release should hold hazardous waste operations training. File each tester's certificate with its report.